Electrical Engineering · Project Management and Estimation
In project cost estimation based on accuracy levels, which type of estimate requires the project scope to be highly defined, aiming for an accuracy range within 0 to 5%?
- 1Order of magnitude estimate
- 2Preliminary estimate
- 3Definitive estimate✓
- 4Feasibility estimate
Correct answer
Definitive estimate