In Program Evaluation and Review Technique (PERT), the formula to calculate the expected mean time (te) for an activity is:
- 1te = Optimistic Time + Pessimistic Time + 4 × Most Likely Time6✓
- 2te = Optimistic Time + Pessimistic Time + 4 × Most Likely Time
- 3te = 4 × (Optimistic Time + Pessimistic Time + Most Likely Time)
- 4te = Optimistic Time + 4 × Pessimistic Time + Most Likely Time6
Correct answer
te = Optimistic Time + Pessimistic Time + 4 × Most Likely Time6
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Operations Research?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Operations Research