In production planning and control, 'loading' is best defined as:
- 1Uploading a part program into the machine tool control unit
- 2Transporting the finished goods from the shop floor to the final warehouse
- 3Sending the raw materials from the receiving dock to the primary store
- 4Assigning specific work or volume of work to specific production facilities or machines✓
Correct answer
Assigning specific work or volume of work to specific production facilities or machines
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Industrial Engineering?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Industrial Engineering