In post-installed rebars using epoxy injection, the minimum embedment length should fundamentally be based on:
- 1Half the bar diameter
- 2Tensile specifications of IS 1786
- 3General structural site drawing only
- 4Development length requirements as per IS 456✓
Correct answer
Development length requirements as per IS 456