Computer · Construction Management
In PERT (Programme Evaluation and Review Technique), when the duration of an activity is uncertain, which time estimate is used for network calculations?
- 1Pessimistic time
- 2Expected time✓
- 3Most likely time
- 4Optimistic time
Correct answer
Expected time
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Management