In PERT (Program Evaluation and Review Technique) analysis, the time estimates of individual activities are assumed to follow which probability distribution curve?
- 1Binomial distribution curve
- 2Normal distribution curve
- 3β-distribution curve✓
- 4Poisson's distribution curve
Correct answer
β-distribution curve