Mathematics · PERT Network Analysis
In PERT network analysis, while an individual activity time follows a Beta distribution, the probability distribution taken to represent the total project completion time is the:
- 1Beta distribution
- 2Gamma distribution
- 3Exponential distribution
- 4Normal distribution✓
Correct answer
Normal distribution