In PERT, how is the expected time (TE) for an activity calculated?
- 1TE = (Optimistic time + 2 × Most likely time + Pessimistic time) / 3
- 2TE = (Optimistic time + Most likely time + Pessimistic time) / 3
- 3TE = (Optimistic time + 4 × Most likely time + Pessimistic time) / 6✓
- 4TE = (Optimistic time + 2 × Most likely time + Pessimistic time) / 4
Correct answer
TE = (Optimistic time + 4 × Most likely time + Pessimistic time) / 6
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Industrial Engineering and Operations Research?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Industrial Engineering and Operations Research