In network scheduling, the Earliest Finish Time (EFT) of an activity is calculated as:
- 1Earliest Start Time − Activity Duration
- 2Earliest Start Time + Activity Duration✓
- 3Latest Finish Time + Activity Duration
- 4Latest Finish Time − Activity Duration
Correct answer
Earliest Start Time + Activity Duration