In network crashing, to optimize project duration efficiently, crashing which type of activity will reduce project time with the minimum additional cost?
- 1Costliest and critical activity
- 2Costliest and non-critical activity
- 3Critical activity with the minimum cost slope✓
- 4Cheapest and non-critical activity
Correct answer
Critical activity with the minimum cost slope