In network analysis, two methods A and B have the following characteristics: Method A: Project cost increases if time duration is either increased or decreased. Method B: Project cost varies directly with time. Method A and Method B are respectively called:
- 1PERT and PERT
- 2PERT and CPM
- 3CPM and CPM
- 4CPM and PERT✓
Correct answer
CPM and PERT