Computer · Construction Management
In network analysis, total float or slack represents the difference between the:
- 1Earliest completion time and earliest start time
- 2Latest allowable time and earliest completion time✓
- 3Earliest completion time and normal expected time
- 4Latest allowable time and normal expected time
Correct answer
Latest allowable time and earliest completion time