In network analysis, select the INCORRECT statement regarding activities and nodes from the following options:
- 1The earliest finish of an activity is the late event time of the node it enters minus its duration.✓
- 2The latest start of an activity is its latest finish minus its duration.
- 3The latest finish of an activity is the late event time of the node it enters.
- 4The earliest start of an activity is the early event time of the node it leaves.
Correct answer
The earliest finish of an activity is the late event time of the node it enters minus its duration.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Project Management