Computer · Project Management
In network analysis frameworks like CPM/PERT, an artificial activity used to show that an activity cannot start until a preceding one is complete, consuming zero time and resources, is known as a:
- 1Free float
- 2Critical event
- 3Total float
- 4Dummy activity✓
Correct answer
Dummy activity