In network analysis, float or slack represents the difference between the:
- 1Latest allowable time and normal allowable time
- 2Earliest completion time and normal expected time
- 3Latest allowable time and earliest completion time✓
- 4Earliest completion time and latest allowable time
Correct answer
Latest allowable time and earliest completion time