In network analysis and scheduling, 'Lag time' is defined as the:
- 1time by which a preceding event must be completed.
- 2minimum delay required between the start or finish of a predecessor activity and the start or finish of its successor activity.✓
- 3time spent performing more critical activities in parallel.
- 4measure of the excess time resources available for a non-critical activity.
Correct answer
minimum delay required between the start or finish of a predecessor activity and the start or finish of its successor activity.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Management