In job-shop or make-to-order manufacturing operations, the Master Production Schedule (MPS) is usually expressed in terms of:
- 1specific customer orders✓
- 2generic component kits
- 3assembled sub-modules
- 4standardized end items
Correct answer
specific customer orders