In detailed cost estimation, what does the term 'contingency' refer to?
- 1Contractor's profit
- 2An allowance for unexpected expenditure during the execution of the work✓
- 3The direct cost of labour and materials
- 4Total cost of the project
Correct answer
An allowance for unexpected expenditure during the execution of the work