Computer · Estimating and Costing
In detailed cost estimation, what does the term 'contingency' refer to?
- 1Total cost of the project
- 2The direct cost of labor and materials
- 3An allowance for unexpected expenditure during execution✓
- 4Contractor's profit
Correct answer
An allowance for unexpected expenditure during execution
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Estimating and Costing?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Estimating and Costing