In Critical Path Method (CPM), the cost slope is determined by which of the following formulas?
- 1Crash Cost Normal Cost
- 2Crash Cost - Normal Cost Normal Time - Crash Time✓
- 3Normal Cost Crash Cost
- 4Normal Time - Crash Time Crash Cost - Normal Cost
Correct answer
Crash Cost - Normal Cost Normal Time - Crash Time