In Critical Path Method (CPM) analysis, 'total float' refers to the:
- 1difference between the earliest start and earliest finish times of an activity.
- 2time saved by performing non-critical activities in parallel.
- 3buffer added to the project to account for uncertainties in activity durations.
- 4maximum time an activity can be delayed without delaying the project completion date.✓
Correct answer
maximum time an activity can be delayed without delaying the project completion date.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Industrial Engineering and Operations Research?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Industrial Engineering and Operations Research