General Studies · Project Crashing
In CPM's 'crashing' strategy, what is the fundamental trade-off that a project manager must evaluate?
- 1The trade-off between additional resource cost incurred and the reduction in project duration achieved on the critical path✓
- 2The trade-off between deterministic and probabilistic time estimation approaches
- 3The trade-off between the number of activities on the critical path and the total float available
- 4The trade-off between project scope and number of stakeholders involved
Correct answer
The trade-off between additional resource cost incurred and the reduction in project duration achieved on the critical path
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Crashing?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Project Crashing