In construction contracts, 'liquidated damages' refers to the:
- 1Damages to walls, plasters, and paints caused by water logging or rain leakage
- 2Penalty cost required to rectify dampness in buildings arising from heavy rainfall
- 3Penalty cost imposed to correct sub-standard quality of completed work
- 4Pre-estimated compensation or penalty for delaying the work beyond the agreed completion date✓
Correct answer
Pre-estimated compensation or penalty for delaying the work beyond the agreed completion date
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Contracts and Tenders?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Contracts and Tenders