Computer · Estimating and Costing
In construction contracts and estimation, 'Prime Cost' refers to:
- 1The net actual cost of specialized articles or materials at a shop/supplier✓
- 2The total actual cost of executing the entire labor contract on-site
- 3The annual interest accrued on non-perishable articles
- 4The fixed percentage profit allocated for the total actual work done
Correct answer
The net actual cost of specialized articles or materials at a shop/supplier
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Estimating and Costing?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Estimating and Costing