Electrical Engineering · Estimating and Costing
In basic electrical estimation for commercial buildings, how is the total internal installation labour cost calculated?
- 12 × (Labour cost for point wiring + Labour cost for fabricating switchboards)
- 22 × (Labour cost for point wiring × Labour cost for fabricating switchboards)
- 3Labour cost for point wiring × Labour cost for fabricating switchboards
- 4Labour cost for point wiring + Labour cost for fabricating switchboards/distribution boards✓
Correct answer
Labour cost for point wiring + Labour cost for fabricating switchboards/distribution boards
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Electrical Engineering?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Estimating and Costing?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Electrical Engineering · Estimating and Costing