Electrical Engineering · Power System Operation and Control
In an electrical power grid, an 'Under frequency' condition occurs when:
- 1the total MW generated is equal to the total load
- 2the total MW generated is less than the total load✓
- 3the total MW generated is more than the total load
- 4the total MW generated is zero
Correct answer
the total MW generated is less than the total load