In a standard costing system, management observes a discrepancy in the fixed overhead volume variance despite the actual output aligning perfectly with the budgeted units. The variance arose because actual labor hours worked were lower than budgeted due to automated robotic efficiency. Which specific sub-component of the variance explains this when overhead is absorbed based on labor hours?
- 1Fixed Overhead Calendar Variance
- 2Fixed Overhead Efficiency Variance✓
- 3Fixed Overhead Capacity Variance
- 4Fixed Overhead Expenditure Variance
Correct answer
Fixed Overhead Efficiency Variance
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Economics?
Practice full-length Economics mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Cost Accounting?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Economics · Cost Accounting