Mathematics · PERT CPM Network Analysis
In a standard AON/AOA project network diagram where event numbers are sequentially ordered from start to finish (such that arrows head towards higher numbers), which of the following general statements about event precedence is incorrect?
- 1Event 5 follows event 3
- 2Event 7 preceded event 6✓
- 3Event 7 can occur after event 4
- 4Events 3 and 4 occur after event 2
Correct answer
Event 7 preceded event 6
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on PERT CPM Network Analysis?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · PERT CPM Network Analysis