In a sand replacement test, the weight of sand required to fill the pit is 600 g. The dry unit weight of the standard calibrating sand is 1.5 g/cm3. If the weight of the excavated soil from the pit is 750 g, find the in-situ wet unit weight of the soil.
- 12.5 g/cm3
- 21.6 g/cm3
- 31.875 g/cm3✓
- 42.2 g/cm3
Correct answer
1.875 g/cm3