Computer · Soil Mechanics
In a Plate Load Test, after every increment in load on the plate, settlements are recorded till the rate of settlement is less than ________ and thereafter the load is increased and the test is continued until a load of about ________ times the anticipated ultimate load is applied.
- 10.01 mm/hour, 2
- 20.02 mm/hour, 2
- 30.01 mm/hour, 1.5
- 40.02 mm/minute, 1.5✓
Correct answer
0.02 mm/minute, 1.5