In a penetration macadam type bituminous surfacing, what is the correct sequence of construction?
- 1Placing fine aggregates before bitumen application
- 2Applying bitumen first, then placing and compacting aggregates
- 3Laying coarse aggregates, followed by bitumen application and spreading screenings✓
- 4Premixing bitumen with aggregates, followed by compaction
Correct answer
Laying coarse aggregates, followed by bitumen application and spreading screenings
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Civil Engineering Surveying?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Highway Engineering?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Civil Engineering Surveying · Highway Engineering