In a network diagram, a dummy activity is introduced primarily to ______.
- 1maintain the required logical and grammatical relationships in the network✓
- 2calculate the minimum project completion time
- 3identify the critical path of the network
- 4determine the optimum project cost
Correct answer
maintain the required logical and grammatical relationships in the network