Physics · Transformers
In a direct loading test of a transformer, the transformer is loaded to its rated capacity for a specified number of hours primarily to determine the ________.
- 1voltage sustainability
- 2transformer oil grading
- 3flux density
- 4temperature rise✓
Correct answer
temperature rise