In a decentralized purchasing structure, a significant control risk that the organization must mitigate is:
- 1A lack of specialized expertise for negotiating complex category-specific contracts.
- 2Slower response times to local operational needs.
- 3Higher administrative overhead costs due to duplication of staff.
- 4The potential for inconsistent pricing and terms for the same material across different plant locations.✓
Correct answer
The potential for inconsistent pricing and terms for the same material across different plant locations.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Economics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Purchasing and Store Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Economics · Purchasing and Store Management