Computer · PERT and CPM
In a CPM Network, an estimate that is required to complete a job in the absolute minimum time is called:
- 1Threshold estimate
- 2Normal estimate
- 3Minimum time estimate
- 4Crash estimate✓
Correct answer
Crash estimate