If the optimistic time (to), most likely time (tm), and pessimistic time (tp) for an activity are 2, 5, and 14 days respectively, then its expected duration (te) and variance (σ2) are:
- 12 days and 5 days
- 26 days and 4 days✓
- 314 days and 7 days
- 416 days and 5 days
Correct answer
6 days and 4 days