If the expected time for completion of a project is 10 days with a standard deviation of 2 days, what is the expected time of completion of the project with a 99.9% probability (corresponding to approximately a +3σ limit)?
- 116 days✓
- 210 days
- 36 days
- 44 days
Correct answer
16 days