Mathematics · Estimation and Costing
If sand costs ₹1,000 per cubic meter and cement costs ₹400 per bag, and 1 cubic meter of mortar requires 0.4 cubic meters of sand and 6 bags of cement, what is the total material cost per cubic meter of mortar?
- 1₹4,000
- 2₹3,800
- 3₹2,800✓
- 4₹3,400
Correct answer
₹2,800