If for a given activity, the optimistic time, pessimistic time, and most likely time estimates are 7, 13, and 10 days respectively, what would be the expected time (te) in PERT analysis?
- 18 days
- 29 days
- 310 days✓
- 415 days
Correct answer
10 days