If a capital budgeting project's Profitability Index (PI) is calculated to be 0.95, what does this imply about the project's Net Present Value (NPV) and the resulting investment decision?
- 1The NPV is unrelated to the calculated Profitability Index
- 2The NPV is negative, indicating that the project should be rejected✓
- 3The NPV is exactly zero, making the decision indifferent to the firm
- 4The NPV is positive, indicating that the project should be accepted
Correct answer
The NPV is negative, indicating that the project should be rejected
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Investment Appraisal Techniques?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Investment Appraisal Techniques