Mathematics · Time and Work
If A, B, and C together can complete a piece of work in 20 days and A alone can complete it in 24 days, then in how many days can B and C together complete the same work?
- 1120 days✓
- 245 days
- 330 days
- 460 days
Correct answer
120 days
Download Single Question PDF