Identify the true statement(s): Statement 1: Gantt Chart is also known as the timeline chart of a project. Statement 2: PERT chart helps to determine the Critical Path.
- 1Both 1 & 2✓
- 2Neither 1 nor 2
- 31 only
- 42 only
Correct answer
Both 1 & 2