Economics · Project Management and Network Analysis
Identify the true statement(s) regarding network analysis in project management: 1. The starting point of an activity is called a tail event. 2. A merge event represents the joint completion of more than one activity. 3. A burst event represents the joint starting of more than one activity.
- 11, 2, and 3✓
- 22 and 3 only
- 31 and 2 only
- 41 and 3 only
Correct answer
1, 2, and 3
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Economics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management and Network Analysis?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Economics · Project Management and Network Analysis