Identify the correct statement regarding heads in a hydroelectric power plant setup.
- 1Gross head is the water level before head race.
- 2Gross head is the effective head after the water is delivered.
- 3Net head or effective head is the head available at the inlet of the turbine.✓
- 4Net head is the water level before tail race.
Correct answer
Net head or effective head is the head available at the inlet of the turbine.