Computer · Highway Engineering
Identify the CORRECT sequence of engineering surveys carried out for highway alignment.
- 1Preliminary survey, Final location and detailed surveys, Map study, and Reconnaissance survey
- 2Final location and detailed surveys, Map study, Reconnaissance survey, and Preliminary survey
- 3Reconnaissance survey, Final location and detailed surveys, Map study, and Preliminary survey
- 4Map study, Reconnaissance survey, Preliminary survey, and Final location and detailed surveys✓
Correct answer
Map study, Reconnaissance survey, Preliminary survey, and Final location and detailed surveys
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Highway Engineering?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Highway Engineering