General Studies · Production and Operations Management
Identify the correct sequence of activities involved in the development and functioning of a Quality Circle: A. Constitution of Quality Circle B. Start-up phase C. Presentation and approval of suggestions D. Initial problem solving E. Implementation Choose the correct answer from the options given below:
- 1B, A, D, C, E✓
- 2B, A, C, D, E
- 3A, B, D, E, C
- 4A, D, E, B, C
Correct answer
B, A, D, C, E
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Production and Operations Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Production and Operations Management