General Studies · Project Management
Identify the correct distinguishing features between Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM): 1. CPM is suited for projects with predictable, repetitive activities, whereas PERT is designed for uncertain, non-repetitive activities. 2. PERT utilizes a deterministic model relying on a single time estimate, while CPM uses a probabilistic model. 3. CPM is a method managing both time and cost control, while PERT primarily focuses on the planning and control of time. 4. The concept of 'crashing' (shortening project duration with the least additional cost) is traditionally built into PERT but not into CPM.
- 11, 2, and 3 only
- 21, 3, and 4 only
- 32 and 4 only
- 41 and 3 only✓
Correct answer
1 and 3 only
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Project Management