Identify the correct distinguishing features between Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM): 1. CPM relies on a deterministic model using a single time estimate, whereas PERT utilizes a probabilistic model incorporating three time estimates. 2. PERT places a stronger emphasis on demarcating between critical and non-critical activities compared to CPM. 3. CPM is a dual-purpose method managing both time and cost control, while PERT primarily addresses the planning and control of time. 4. Crashing, a compression technique to shorten project duration with the least additional cost, is applicable to PERT but not to CPM. Choose the correct option:
- 11, 2, and 3 only
- 21, 3, and 4 only
- 32 and 4 only
- 41 and 3 only✓
Correct answer
1 and 3 only
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Management?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Management · Project Management