Accounting · Material and Labour Budgeting
House Co. plans to manufacture 90 sofas in June. Below are extracts from the cost card for a sofa: - Materials: 10 m² of fabric @ $50 per m² - Assembly labour: 8 hours @ $15 per hour How many metres of fabric should be purchased if 10% of material is wasted during the production process, and how much should be budgeted for labour for sofa production in June?
- 1(i) 900 m², (ii) $10,800
- 2(i) 1,000 m², (ii) $10,700
- 3(i) 1,000 m², (ii) $10,800✓
- 4(i) 1,100 m², (ii) $12,000
Correct answer
(i) 1,000 m², (ii) $10,800
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Accounting?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Material and Labour Budgeting?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Accounting · Material and Labour Budgeting