'HomeBuild Construction Ltd.' undertakes a complex, multi-year housing project. The company sub-contracts the electrical installation work to 'PowerConnect Pvt. Ltd.' under a separate, specific job agreement. Which specific costing methods should HomeBuild Construction Ltd. (the main contractor) and PowerConnect Pvt. Ltd. (the sub-contractor for the specific job) use, respectively?
- 1HomeBuild: Process Costing; PowerConnect: Single Output Costing
- 2HomeBuild: Job Costing; PowerConnect: Process Costing
- 3HomeBuild: Contract Costing; PowerConnect: Job Costing✓
- 4HomeBuild: Single Output Costing; PowerConnect: Batch Costing
Correct answer
HomeBuild: Contract Costing; PowerConnect: Job Costing
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Business Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Methods of Costing?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Business Studies · Methods of Costing